Ethiopia Workshop

The steel structure workshop, located in Bahir Dar city,Ethiopia. The size of the workshop is 150m*50m*8m, Total 7500SQM. This Industrial Park workshop will promote the realization of Ethiopia’s industrialization goals, create more favorable conditions for Ethiopia to attract investment, create more employment opportunities, upgrade work skills and improve living standards.


  • Project size: 150*50*8 M
  • Location: Bahir Dar ,Ethiopia
  • Application: Industrial park workshop
  • Project Introduction

    The steel structure workshop, located in Bahir Dar city,Ethiopia. The size of the workshop is 150m*50m*8m, Total 7500SQM. This Industrial Park workshop will promote the realization of Ethiopia's industrialization goals, create more favorable conditions for Ethiopia to attract investment, create more employment opportunities, upgrade work skills and improve living standards.

    case6 (4)

    case6 (5)

    case6 (3)

    case6 (6)

    Design Parameter

    The below information are the parameters of different parts:
    Workshop building :Wind load≥0.65KN/M2 ,Live load≥0.55KN/M2 ,Dead load≥0.15KN/M2.
    Steel beam &column(Q355 steel):2 layers epoxy antirust oil painting in 130μm thickness color is red
    Roof&wall sheet:corrugated galvanized sheet(V-840 and V900) White color
    Roof&wall purlin(Q345 steel) :C section Galvanized Steel Purlin
    Door size is 5*5m sliding door, which can be open and close easily.
    This workshop has big size windows which can help workshop inside lighting well.

    Production & Shipping

    We prepared all steel parts for client during 36 days, and packed loaded in 10*40HC containers. Shipping time is 42 days to Djibouti port. Client use ESL(Ethiopian Shipping and Logistics Service Enterprise) and get containers from Modjo/ commet DRY PORT,then use trucks take to his project site.

    Installation

    The owner used our company installation team to install the steel structure parts, it cost 54 days totally to finish the foundation and installation work.

    Execute Summary

    From client contact us to project done ,It took a total of 132 day.This is a project with a very fast construction cycle for customers in Ethiopia. Our company are responsible for project design, material processing, and transportation, installation.

    Client Feedback

    The local government spokesman said that he was very pleased to see such excellent projects in Ethiopia and hoped that there would be more similar projects in the future to continue to promote the development of Ethiopian industrial parks.